How long will it take to build out the network, and when will services be available?

The next steps from Lumos are to formulate a more detailed engineering plan, which will take several months. The entire build – including the RFP and Lumos's privately financed portion – is scheduled to be finished by the end of 2025, barring unforeseen circumstances.

The construction timeline would make services available to homes within the RFP according to the following schedule:

PhaseHomes addedDate
11,000June 30, 2023
21,000Sept. 30, 2023
31,000Dec. 31, 2023
41,000March 31, 2024
51,000June 30, 2024
61,370Sept. 30, 2024

Show All Answers

1. Now that Phase I has been announced, what happens next?
2. How long will it take to build out the network, and when will services be available?
3. Will Lumos offer a low-cost option?
4. I live on a private road – what can I do to get service?
5. I want to sign up. What do I do?
6. My home is far off the main road – what can I do?
7. What kinds of service options are available, and what is the cost?
8. Why did Orange County decide Broadband was a priority?
9. Why did Orange County choose to partner with Lumos?
10. How is Orange County paying for its share?
11. What will Lumos do?