Orange County will host a neighborhood information meeting on Thursday, Sept. 12, at the Link Building (200 S. Cameron Street, Hillsborough) to update residents of the status of the Northern County Campus project. The meeting will be from 5-6 p.m.
Staff from the county as well as representatives from the Construction Manager at Risk will be on hand to provide information and answer questions. Maps and drawings of the project will be available. The campus is located off Highway 70 in Hillsborough.
In February 2019, the Board of Commissioners reviewed schematic design cost estimates for the Northern County Campus and authorized a total budget of $40.2 million. Substantial completion is scheduled for March 2021, and final completion is scheduled for May 2021.
The Northern County Campus project includes three primary components: